Live project status across SACAP Stages 1–6
Stages & activities
Click a stage to expand · click any activity to pin & adjust it
Scenario & changes
Your current working assumptions
What's next
Upcoming from today · click to pin

Welcome to the RCS3D Project Tracker

The RCS3D Project Tracker is a live console for the SACAP Stage 1–6 programme for the HOA office facilities — schedule, progress, team load, analytics and meeting tools in one place. It's a single self-contained file, nothing to install. Your edits (start date, progress, custom dates, notes) are saved privately in this browser and never change the underlying brief.

Quick start?

  1. Set a realistic start date. Use “Project starts” at the top-right to slide the whole programme to a workable date and instantly see the new finish.
  2. Track progress. Open Edit dates & progress (left menu) and drag each activity's slider. The completion ring and health metrics update live.
  3. Model a change. Switch Schedule to Custom, adjust a task, and the original plan appears as a dashed “ghost” with a ± day difference.
  4. Share it. Use Share to WhatsApp for a summary card, or Save as image / Print / PDF for a snapshot.

The four views?

  • Overview? — health at a glance and per-stage progress.
  • Timeline? — the Gantt chart with zoom, filter & search.
  • Team & Load? — who owns what, and when they're busy.
  • Analytics? — charts & schedule intelligence.

Key features?

  • Master start-date shifter?
  • Per-task progress tracking?
  • Custom vs actual comparison?
  • Live completion ring & health?
  • Week / Month / Year zoom?
  • Freeze cards & notes?
  • Per-contractor view?
  • Excel working file?
  • Search & stage filter?
  • Meeting minutes?
  • WhatsApp / image / PDF?
  • Reset all changes?

* About the asterisk

Activities marked with an amber * were added by RCS3D to fill gaps in the source brief — currently the two drafting activities in Stages 3 & 4, which the brief mentioned but the schedule folded into the stage headers.

They are best-estimate placeholders so the plan and the Drafting Team's workload look complete. Caren (principal agent) should review these dates and durations and confirm or adjust them before the plan is issued.

Tip: everything is reversible — Reset all changes in the left menu restores the original brief.

0 activities adjusted

Notes

Compiled from your saved changes & notes

Notes & adjustments

Every note and schedule change saved in this browser

Edit dates & progress

Model a revised schedule and track completion. Setting a stage's progress cascades to all its activities (you can still fine-tune any one after). Changes save in this browser and drive the comparison view, health metrics and completion ring. Nothing here alters the source data.
TaskActual start → endCustom startDurationProgress